Grand Colorado on Peak 8 Property Information

Letter from the Construction Manager

  • Phase 1 plaza and terrace units insulation and drywall are 80 percent complete.
  • The exterior sheeting, siding and trim on the North and West faces in Phase 1 are complete.
  • The sheetrock is hung in Phase 1 units. Texture and painting will begin in January.
  • The second- and third-floor unit fireplaces in Phase 1 units are operational.
  • Shells for the indoor pools and hot tubs are complete in Phase 1.
  • The common area mechanical, electrical and plumbing (MEP) are complete in Phase 1. A grease duct is being installed up through the Phase 1 building.
  • Phase 1 and 2 masonry work is in progress. So far, two chimneys have been completed.
  • Exterior framing work is still in progress on Phase 3.

Deb Norton
Construction Manager, Grand Colorado on Peak 8 

GC8_BookingReminder

Grand Colorado on Peak 8 Property Information

003Letter from the Construction Manager:

  • The insulation is in progress and the drywall is 50 percent complete in the Phase 1, plaza and terrace units.
  • The exterior sheathing, siding, and trim is still in progress in Phase 1.
  • Majority of sheetrock is hung in Phase 1 units.
  • Phase 1, 2nd floor unit fireplaces are operational.
  • Exterior sheathing is now in progress for Phase 2.
  • Exterior framing is in progress for Phase 3.
  • Work on the pools and spas is in progress.
  • Mechanical, electrical and plumbing rough-ins have been started in the common areas in Phase 1.

Deb Norton
Grand Colorado on Peak 8 Construction Manager

GC8_BookingReminder

Grand Colorado on Peak 8 Property Information

IMG_3869 IMG_3876Letter from the Construction Manager:

  • We have poured the concrete on the 4th floor in Phase 3.
  • The steel “super structure” is complete.
  • The plaza and terrace common areas are framed and the windows are installed in Phase 1.
  • The drywall is 75% complete in Phase 1.
  • We are continuing to make progress on the exterior trim and siding work.
  • The exterior walls in Phase 2 are framed.
  • The pool shells are under construction.
  • The mechanical room and boiler flue are almost complete.
  • The exterior stairway from the ski area to the pool courtyard is installed.
  • The lobby stair structure is in place.

 

Grand Colorado on Peak 8 Property Information

003 014 028Letter from the Construction Manager:

  • Concrete floors have been poured on the Phase 3 second floor.
  • Steel “super structure” is complete except for few minor details.
  • The Cooling Towner, an air-conditioning unit for the building, has been placed on the roof.
  • Building back fill of about 14’ for the driveway entrance into the garage has been placed.
  • The plaza and terrace units in Phase 1 are framed and the windows and sliding doors have been installed.
  • Drywall is being installed in Phase 1 on the fourth floor.
  • Exterior trim and siding work is still underway on Phase 1.
  • Waterproofing of the pool “shell” has been completed.

Deb Norton
Grand Colorado on Peak 8 Construction Manager

Grand Colorado on Peak 8 Property Information

Letter from the Construction Manager:

  • We have completed the concrete structural slab through 1F, Phase 3.
  • The roof steel is 98% complete through Phase 3.We will demobilize the crane next week.
  • The drywall and ceiling framing continue to be installed on 2F – 4F, Phase 1.
  • The windows and sliding doors are about 80% installed, Phase 1.
  • The framing is close to completion in the “triangle” area, Phase 1.
  • The exterior trim and siding has started this past month.
  • The indoor/outdoor pool installation work has begun. We are working on the waterproofing and plumbing of the “shells” at this time.

Deb Norton
Grand Colorado on Peak 8 Construction Manager

 

Grand Colorado on Peak 8 Property Information

Letter from the Construction Manager

  • We have poured the concrete for 3F and 4F, Phase 2
  • The steel roof is 95% complete
  • The Phase 3 steel is approximately 55% complete
  • The roofers will begin drying in the roof next week
  • The elevator company is on-site to begin installation of elevators 1 and 2
  • The drywall work continues in the residential areas, 2F – 4F
  • The sliding glass doors in the residential units are being installed
  • The framing is complete on 5F and the Sales Center
  • We are spraying the fireproofing in Phase 2 now
  • The concrete work continues in the pool area in preparation for the pool installers

Deb Norton
Grand Colorado on Peak 8 Construction Manager