Grand Colorado on Peak 8 Property Information

003Letter from the Construction Manager:

  • The insulation is in progress and the drywall is 50 percent complete in the Phase 1, plaza and terrace units.
  • The exterior sheathing, siding, and trim is still in progress in Phase 1.
  • Majority of sheetrock is hung in Phase 1 units.
  • Phase 1, 2nd floor unit fireplaces are operational.
  • Exterior sheathing is now in progress for Phase 2.
  • Exterior framing is in progress for Phase 3.
  • Work on the pools and spas is in progress.
  • Mechanical, electrical and plumbing rough-ins have been started in the common areas in Phase 1.

Deb Norton
Grand Colorado on Peak 8 Construction Manager

GC8_BookingReminder

Grand Colorado on Peak 8 Property Information

IMG_3869 IMG_3876Letter from the Construction Manager:

  • We have poured the concrete on the 4th floor in Phase 3.
  • The steel “super structure” is complete.
  • The plaza and terrace common areas are framed and the windows are installed in Phase 1.
  • The drywall is 75% complete in Phase 1.
  • We are continuing to make progress on the exterior trim and siding work.
  • The exterior walls in Phase 2 are framed.
  • The pool shells are under construction.
  • The mechanical room and boiler flue are almost complete.
  • The exterior stairway from the ski area to the pool courtyard is installed.
  • The lobby stair structure is in place.

 

Grand Colorado on Peak 8 Property Information

003 014 028Letter from the Construction Manager:

  • Concrete floors have been poured on the Phase 3 second floor.
  • Steel “super structure” is complete except for few minor details.
  • The Cooling Towner, an air-conditioning unit for the building, has been placed on the roof.
  • Building back fill of about 14’ for the driveway entrance into the garage has been placed.
  • The plaza and terrace units in Phase 1 are framed and the windows and sliding doors have been installed.
  • Drywall is being installed in Phase 1 on the fourth floor.
  • Exterior trim and siding work is still underway on Phase 1.
  • Waterproofing of the pool “shell” has been completed.

Deb Norton
Grand Colorado on Peak 8 Construction Manager

Grand Colorado on Peak 8 Property Information

Letter from the Construction Manager:

  • We have completed the concrete structural slab through 1F, Phase 3.
  • The roof steel is 98% complete through Phase 3.We will demobilize the crane next week.
  • The drywall and ceiling framing continue to be installed on 2F – 4F, Phase 1.
  • The windows and sliding doors are about 80% installed, Phase 1.
  • The framing is close to completion in the “triangle” area, Phase 1.
  • The exterior trim and siding has started this past month.
  • The indoor/outdoor pool installation work has begun. We are working on the waterproofing and plumbing of the “shells” at this time.

Deb Norton
Grand Colorado on Peak 8 Construction Manager

 

Grand Colorado on Peak 8 Property Information

Letter from the Construction Manager

  • We have poured the concrete for 3F and 4F, Phase 2
  • The steel roof is 95% complete
  • The Phase 3 steel is approximately 55% complete
  • The roofers will begin drying in the roof next week
  • The elevator company is on-site to begin installation of elevators 1 and 2
  • The drywall work continues in the residential areas, 2F – 4F
  • The sliding glass doors in the residential units are being installed
  • The framing is complete on 5F and the Sales Center
  • We are spraying the fireproofing in Phase 2 now
  • The concrete work continues in the pool area in preparation for the pool installers

Deb Norton
Grand Colorado on Peak 8 Construction Manager

,

Grand Colorado on Peak 8 Property Information

6.7.15_4 6.7.15_7 6.7.15_11Construction on Grand Colorado on Peak 8 is well underway. As of June 30 the following has been taking place:

  • Concrete work will be complete in Phase 1 over the next 2 – 3 weeks
  • Steel is set through Phase 2 and we have started on 1F and 2F in Phase 3
  • The framing is 90% complete in the Phase 1 residential units, 2F – 5F
  • We began hanging drywall in the residential units, 2F
  • Fireplaces are being installed in the residential units, 2F – 3F
  • The windows continue to be installed
  • Exterior fascia and window trim is being installed in Phase 1
  • Work will begin in earnest on the pools, etc. within a couple of weeks