Grand Colorado on Peak 8 Property Information

Letter from the Construction Manager:

  • We have completed the concrete structural slab through 1F, Phase 3.
  • The roof steel is 98% complete through Phase 3.We will demobilize the crane next week.
  • The drywall and ceiling framing continue to be installed on 2F – 4F, Phase 1.
  • The windows and sliding doors are about 80% installed, Phase 1.
  • The framing is close to completion in the “triangle” area, Phase 1.
  • The exterior trim and siding has started this past month.
  • The indoor/outdoor pool installation work has begun. We are working on the waterproofing and plumbing of the “shells” at this time.

Deb Norton
Grand Colorado on Peak 8 Construction Manager

 

Grand Colorado on Peak 8 Property Information

Letter from the Construction Manager

  • We have poured the concrete for 3F and 4F, Phase 2
  • The steel roof is 95% complete
  • The Phase 3 steel is approximately 55% complete
  • The roofers will begin drying in the roof next week
  • The elevator company is on-site to begin installation of elevators 1 and 2
  • The drywall work continues in the residential areas, 2F – 4F
  • The sliding glass doors in the residential units are being installed
  • The framing is complete on 5F and the Sales Center
  • We are spraying the fireproofing in Phase 2 now
  • The concrete work continues in the pool area in preparation for the pool installers

Deb Norton
Grand Colorado on Peak 8 Construction Manager

,

Grand Colorado on Peak 8 Property Information

6.7.15_4 6.7.15_7 6.7.15_11Construction on Grand Colorado on Peak 8 is well underway. As of June 30 the following has been taking place:

  • Concrete work will be complete in Phase 1 over the next 2 – 3 weeks
  • Steel is set through Phase 2 and we have started on 1F and 2F in Phase 3
  • The framing is 90% complete in the Phase 1 residential units, 2F – 5F
  • We began hanging drywall in the residential units, 2F
  • Fireplaces are being installed in the residential units, 2F – 3F
  • The windows continue to be installed
  • Exterior fascia and window trim is being installed in Phase 1
  • Work will begin in earnest on the pools, etc. within a couple of weeks

 

, , ,

By the Numbers

Every wonder about the small details with Breckenridge Grand Vacations properties? Take a look at some of the fun facts about each property!

Grand Colorado on Peak 8 Property Information

May was an exceptionally wet month full of rain, hail and even snow! But even with the above average precipitation we are happy to report that we were able to keep working and look forward to continual progress in June and July with the installation of the doors, windows and drywall. These changes will start bringing Grand Colorado on Peak 8 to life.  Before you know it, we will be opening those doors and welcoming you home.

Construction Progress Updates:

  • The structural steel is 98 percent complete in phase one and 80 percent complete in phase two.
  • The windows and doors are being installed.
  • Floors 2 and 3 are scheduled for their mechanical rough inspections by July 1 and drywall installation will follow.
  • Installing the pool shells and mechanical are to commence in July.
  • We started the exterior wood siding.

Grand Colorado on Peak 8 Property Information

GC86GC85Letter from the Project Coordinator

With summer on the way, the warmer weather has allowed us to make a lot of progress on the structural steel. We are looking forward to minimal interruptions this summer, with only afternoon showers to think about, and encourage you to head up to the base of Peak 8 to see all of our progress!

Property Updates:

  • We are putting up the structural steel for phase 2 and the phase 1 triangle that contains the plaza and terrace units, the restaurant and the ski lockers.
  • Mechanical and electrical rough-in are close to completion on floor 2 and continues on the upper floors.
  • The doors, windows and exterior sheathing of phase 1 is 95 percent complete.
  • We have confirmed the exterior material selection and this work will begin in the month of May.

Deb Norton
Grand Colorado on Peak 8 Project Coordinator