By the Numbers

Every wonder about the small details with Breckenridge Grand Vacations properties? Take a look at some of the fun facts about each property!

Grand Colorado on Peak 8 Property Information

May was an exceptionally wet month full of rain, hail and even snow! But even with the above average precipitation we are happy to report that we were able to keep working and look forward to continual progress in June and July with the installation of the doors, windows and drywall. These changes will start bringing Grand Colorado on Peak 8 to life.  Before you know it, we will be opening those doors and welcoming you home.

Construction Progress Updates:

  • The structural steel is 98 percent complete in phase one and 80 percent complete in phase two.
  • The windows and doors are being installed.
  • Floors 2 and 3 are scheduled for their mechanical rough inspections by July 1 and drywall installation will follow.
  • Installing the pool shells and mechanical are to commence in July.
  • We started the exterior wood siding.

Grand Colorado on Peak 8 Property Information

GC86GC85Letter from the Project Coordinator

With summer on the way, the warmer weather has allowed us to make a lot of progress on the structural steel. We are looking forward to minimal interruptions this summer, with only afternoon showers to think about, and encourage you to head up to the base of Peak 8 to see all of our progress!

Property Updates:

  • We are putting up the structural steel for phase 2 and the phase 1 triangle that contains the plaza and terrace units, the restaurant and the ski lockers.
  • Mechanical and electrical rough-in are close to completion on floor 2 and continues on the upper floors.
  • The doors, windows and exterior sheathing of phase 1 is 95 percent complete.
  • We have confirmed the exterior material selection and this work will begin in the month of May.

Deb Norton
Grand Colorado on Peak 8 Project Coordinator

 

Grand Colorado on Peak 8 Property Information

We’re proud to say that construction at the Grand Colorado on Peak 8 is on track! The warm weather and bluebird skies have been to our advantage allowing us to make continual progress on your dream resort!  Here are a few updates from the past month:

 Phase 1:

  • We have started the exterior sheathing on the 3rd floor
  • We have begun the roofing insulation
  • We have started installing the windows and sliding doors in the residential units
  • The interior metal framing is 90 percent complete in the residential units
  • The boilers have arrived
  • The main electrical panels are being installed
  • The installation of scaffolding is complete
  • The exterior metal framing is complete

 Phase 2:

  • We have started the concrete flatwork on the 1st floor
  • The structural steel is complete throughout the 1st floor

Deb Norton
Grand Colorado on Peak 8 Project Coordinator

 

Grand Colorado Progress Pictures:

Grand Colorado on Peak 8 Property Information

Construction Update: 

  • Steel work is 95 percent complete in Phase 1, and complete through the 1st and 2nd floor of Phase 2.
  • Fireproofing is 90 percent completed in Phase 1.
  • Interior metal framing is complete through the 4th floor in Phase 1.
  • Mechanical, plumbing and electrical work continues, following framing and the dry-in progress.
  • Scaffolding continues to be installed and is currently tented in plastic.
  • Viewing platform is complete.

Deb Norton
Grand Colorado on Peak 8 Project Coordinator

Grand Colorado on Peak 8 Property Information

gc8_feb[1]Construction Update

  • Progress continues on the steel work.
  • Installing roof decking in Phase 1 has begun.
  • Fireproofing has started on the 2nd and 3rd floors.
  • Interior metal framing has started on the 2nd and 3rd floors for the residential units.
  • Mechanical, electrical and plumbing progress continues.
  • Scaffolding is being installed for future siding and window installation.

Deb Norton
Grand Colorado on Peak 8 Project Coordinator