IMG_3869 IMG_3876Letter from the Construction Manager:

  • We have poured the concrete on the 4th floor in Phase 3.
  • The steel “super structure” is complete.
  • The plaza and terrace common areas are framed and the windows are installed in Phase 1.
  • The drywall is 75% complete in Phase 1.
  • We are continuing to make progress on the exterior trim and siding work.
  • The exterior walls in Phase 2 are framed.
  • The pool shells are under construction.
  • The mechanical room and boiler flue are almost complete.
  • The exterior stairway from the ski area to the pool courtyard is installed.
  • The lobby stair structure is in place.