Letter from the Construction Manager:
- The insulation is in progress and the drywall is 50 percent complete in the Phase 1, plaza and terrace units.
- The exterior sheathing, siding, and trim is still in progress in Phase 1.
- Majority of sheetrock is hung in Phase 1 units.
- Phase 1, 2nd floor unit fireplaces are operational.
- Exterior sheathing is now in progress for Phase 2.
- Exterior framing is in progress for Phase 3.
- Work on the pools and spas is in progress.
- Mechanical, electrical and plumbing rough-ins have been started in the common areas in Phase 1.
Deb Norton
Grand Colorado on Peak 8 Construction Manager