Letter from the Construction Manager
- Phase 1 plaza and terrace units insulation and drywall are 80 percent complete.
- The exterior sheeting, siding and trim on the North and West faces in Phase 1 are complete.
- The sheetrock is hung in Phase 1 units. Texture and painting will begin in January.
- The second- and third-floor unit fireplaces in Phase 1 units are operational.
- Shells for the indoor pools and hot tubs are complete in Phase 1.
- The common area mechanical, electrical and plumbing (MEP) are complete in Phase 1. A grease duct is being installed up through the Phase 1 building.
- Phase 1 and 2 masonry work is in progress. So far, two chimneys have been completed.
- Exterior framing work is still in progress on Phase 3.
Deb Norton
Construction Manager, Grand Colorado on Peak 8