Letter from the Construction Manager
- Insulation is complete and drywall is 90 percent complete in Phase 1 plaza and terrace units.
- Exterior sheeting, siding, and trim are complete on floors two through five in Phase 1.
- Texture and painting are complete on the second floor of Phase 1 units.
- Fourth-floor-unit fireplaces are operational in Phase 1.
- Tile installation to begin February 29 on second-floor Phase 1 units.
- Shells for indoor pools and spa #5 are complete.
- Waterfall #3 design is being changed, and design plans are in progress.
- Sales Center and restaurant designs are complete.
- Units are framed on floors two through four in Phase 2.
- Exterior wall framing work is complete in Phase 3.
Deb Norton
Construction Manager, Grand Colorado on Peak 8