IMG_6287 IMG_6280Phase 1 Updates:

  • Waterproofing is scheduled to begin on pool courtyard deck.
  • Stone veneer is complete on north side and work is in process on the south side.
  • Exterior sheathing, siding and trim is complete on floors 2-5.
  • Storefront glass is 50 percent complete on the 1st floor.
  • Drywall texture and painting is complete on floors 2-3 and in process on 4th floor.
  • Ceramic wood flooring, bathroom tile and fireplace surround tile is 50 percent complete on 3rd floor.
  • Structure for waterfall #3 is 80 percent complete.
  • Pool coping stone is being installed on indoor pools.
  • Cabinets delivered on 3rd floor.
  • Doors, hardware and prefinished trim has been ordered for floors 2-4.
  • Mechanical room 90 percent complete. Boiler and chiller startup scheduled for August.
  • Electrical room is 80 percent complete.
  • Pool mechanical room 50 percent complete.

Phase 2 Updates:

  • Units are framed on floors 2-4.
  • Framing is 80 percent complete on 1st floor.
  • Electrical and mechanical rough-in are in process.

Phase 3 Updates:

  • Steel structure 100 percent complete.
  • Exterior wall framing work is complete.
  • Roof dry-in is underway.