Construction Update

Phase 1 Updates:

  • Waterproofing scheduled to begin on pool courtyard deck.
  • Stone veneer is complete on north side. Work is in process on south side.
  • Exterior sheathing, siding and trim are complete on floors 2-5.
  • Storefront glass is complete on 1st floor.
  • Drywall texture and painting are complete on floors 2-4.
  • Ceramic wood flooring, bathroom tile and fireplace surround tile are complete on the 3rd floor.
  • Structure for waterfall #3 is complete.
  • Pool coping stone is being installed in indoor pools.
  • Cabinets delivered to 3rd floor.
  • Doors, hardware and prefinished trim have been ordered for floors 2-4.
  • Mechanical room is 90 percent complete. Boiler and chiller startup are scheduled for August.
  • Electrical room is 80 percent complete.
  • Pool mechanical room is 70 percent complete.

Phase 2 Updates:

  • Units are framed on floors 2-4.
  • Framing is 80 percent complete on 1st floor.
  • Electrical and mechanical rough-in are in process.
  • Drywall is being installed at demising wall.

Phase 3 Updates:

  • Steel structure is 100 percent complete.
  • Exterior wall framing work is complete.
  • Roof dry-in is underway.