Phase 1 Updates:

  • Waterproofing completed on pool deck.
  • Stone veneer is complete on north, south and east sides.
  • Exterior sheathing, siding, and trim are complete on floors 2-5.
  • Shower enclosures are being installed on floors 2-3.
  • Storefront glass is complete on first floor.
  • Drywall texture and painting are complete on floors 2-4 and in process on Plaza.
  • Steal guardrails have been delivered.
  • Ceramic wood flooring, bathroom tile, and fireplace surround tile are complete on floors 2-4.
  • Structure for waterfall #3 is complete.
  • Pool coping stone is being installed in indoor and outdoor pools.
  • Cabinets have been installed on floors 2-4.
  • Doors, hardware, and prefinished trim have been installed on floors 2-3.
  • Mechanical room is 95 percent complete. Boiler and chiller startup are scheduled for August.
  • Electrical room is 90 percent complete.
  • Pool mechanical room is 75 percent complete.

Phase 2 Updates:

  • Units are framed on floors 2-4.
  • Framing is complete on first floor.
  • Electrical and mechanical rough-in are in process.
  • Drywall is being installed at demising wall.
  • Waterproofing has begun on the exterior patio above the lobby.

Phase 3 Updates:

  • Steel structure is 100 percent complete.
  • Exterior wall framing work is complete.
  • Roof dry-in and deck waterproofing are underway.