We’re proud to say that construction at the Grand Colorado on Peak 8 is on track! The warm weather and bluebird skies have been to our advantage allowing us to make continual progress on your dream resort! Here are a few updates from the past month:
Phase 1:
- We have started the exterior sheathing on the 3rd floor
- We have begun the roofing insulation
- We have started installing the windows and sliding doors in the residential units
- The interior metal framing is 90 percent complete in the residential units
- The boilers have arrived
- The main electrical panels are being installed
- The installation of scaffolding is complete
- The exterior metal framing is complete
Phase 2:
- We have started the concrete flatwork on the 1st floor
- The structural steel is complete throughout the 1st floor
Deb Norton
Grand Colorado on Peak 8 Project Coordinator
Grand Colorado Progress Pictures:
Very excited to see the progress. I have had many, MANY friends and family tell me o dump my time shares (I own at Peak 7 as well), but I tell them that BGV knows how to take care of their owners.
I look forward to my first weak at Peak 8!
Daniel