6.7.15_4 6.7.15_7 6.7.15_11Construction on Grand Colorado on Peak 8 is well underway. As of June 30 the following has been taking place:

  • Concrete work will be complete in Phase 1 over the next 2 – 3 weeks
  • Steel is set through Phase 2 and we have started on 1F and 2F in Phase 3
  • The framing is 90% complete in the Phase 1 residential units, 2F – 5F
  • We began hanging drywall in the residential units, 2F
  • Fireplaces are being installed in the residential units, 2F – 3F
  • The windows continue to be installed
  • Exterior fascia and window trim is being installed in Phase 1
  • Work will begin in earnest on the pools, etc. within a couple of weeks

 