Letter from the Construction Manager

  • We have poured the concrete for 3F and 4F, Phase 2
  • The steel roof is 95% complete
  • The Phase 3 steel is approximately 55% complete
  • The roofers will begin drying in the roof next week
  • The elevator company is on-site to begin installation of elevators 1 and 2
  • The drywall work continues in the residential areas, 2F – 4F
  • The sliding glass doors in the residential units are being installed
  • The framing is complete on 5F and the Sales Center
  • We are spraying the fireproofing in Phase 2 now
  • The concrete work continues in the pool area in preparation for the pool installers

Deb Norton
Grand Colorado on Peak 8 Construction Manager